-
Story
-
Resolution: Done
-
High
-
None
As part of ONAP Dublin M3 (API Freeze) Milestone – March 14th, the Architecture Subcommittee has the goal to sign-off the Dublin Architecture document.
Therefore I would like to remind you to book a slot with the Architecture subcommittee as soon as you can.
Stephen Terrill Feb 20 #1095
Hi,
In order to provide guidance of the requested information, this is what was discussed in ArchCom this week:
Brief Project Overview (brief as it should be known)
New component capabilities for Dublin, i.e. the functional enhancements.
New or modified interfaces
If they are modified, are the backwards compatible?
Interface naming (point to an example)
Reference to the interfaces.
What are the system limits?
Involved use cases, architectural capabilities or functional requirements.
Listing of new or impacted models used by the project (for information only).
A good practice that I saw previously was to have a wiki in each project area for the architecture review and we just go through that.