Uploaded image for project: 'ONAP Operations Manager'
  1. ONAP Operations Manager
  2. OOM-2100

Release Candidate 0 Integration and Test

XMLWordPrintable

    • Icon: Epic Epic
    • Resolution: Done
    • Icon: Medium Medium
    • El Alto Release
    • None
    • None
    • R5 RC0 Final Test
    • Done

      RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases.

      Project Team should focus its effort on:

      1. supporting integration testingĀ (complete Health Check and Pair Wise Testing)
      2. closing high priority defects impacting the integration and test effort
      3. supporting Documentation team
        1. release notes
        2. general documentation
      4. Verifying compliance with license scans and release versioning

            melliott melliott
            mtnskiier mtnskiier
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Created:
              Updated:
              Resolved: