Task
-
Resolution: Done
-
Medium
-
None
-
Not started
-
Not started
-
> 2 weeks
Complete 50% E2E testing.
Two test items:
- Intent translation;
- Intent management.
The Integration test has been done. Due to the delay of UUI project, this work will be integrated to ONAP R9.